A commitment is a deal you have already agreed with a vendor: what you are buying, at what price, and for which project. Orders you place later draw against it, so you can see what you committed to and what is left.
Before you start
Your company must have commitments turned on. If Commitments is missing from the top navigation bar, ask your Admin, or contact us.
By default, Admins, Purchasers and Users can open commitments, and Admins and Purchasers can create them. Your company can change this per role in Company Settings.
Every commitment belongs to 1 project and 1 vendor, so you need both before you start.
The types you may see
You may see 1 or both of these, depending on what your company has turned on:
Material Commitment: agreed quantities and unit prices for materials from your Material Database.
Budget Commitment: one budget for a vendor, compared against what has been invoiced.
Concrete supply is tracked separately, in Concrete Batch Tracking under Project Management. It is a separate product and does not appear in this list.
What the Commitments page shows
The table lists every commitment for the project you have selected, or for all projects. Each row is one commitment with one vendor. The columns include Status, Project, Type, Commitment, Vendor, Expiration Date, Total Budgeted, Total ordered, Total Remaining, Total invoiced and Total un-invoiced.
Total Remaining never shows less than 0. If orders have gone past what you committed, open the commitment to see by how much.
From this page you can:
Use the project selector to switch between all projects and a single project.
Use the search box to find a commitment.
Open the filter panel to set Filters, choose Columns, or use Download to export the list.
Click Create to start a new commitment.
Statuses
The chips above the table filter the list by status. The status pill on a row can read slightly differently: Drafted on the filter is Draft on the row.
Drafted: saved, but not submitted yet.
Confirmed: submitted. You can place orders against it.
Partially delivered: some of what was ordered against it has been delivered.
Delivered: everything ordered against it has been delivered.
Closed: still on record, but not available for new orders.
Cancelled: stopped.
Closed and Cancelled are not counted in All.
Inside a material commitment
Each line shows its figures in 2 groups. Under Quantity: Budgeted Qty, Ordered Qty, Delivered Qty, Remaining Qty and Overage Qty. Under Dollars: Budgeted $, Ordered $, Invoiced $, Remaining $ and Overage $.
Ordering more than a line's budgeted quantity does not raise the budget. The extra shows in red in the Overage columns, and Remaining stops at 0. The budget changes only when someone edits the line.
An order line in a different unit from its commitment line, such as boxes against a line kept in each, draws the line down by dollars only. It counts in Ordered $ and Remaining $, not in Ordered Qty. On the order, that line gets no commitment price and no commitment quantity or budget check, so check its price yourself. The commitment line still shows, exports and syncs in its own unit.
Changing a commitment after you submit it
Lines on a confirmed commitment stay editable for anyone with permission to edit commitments. Make the change, then click Update.
Once orders draw on a line, SubBase protects what they rely on. You cannot lower the line below what is ordered, change its unit, or remove it. The message starts These lines are already on orders and names the orders.
Placing orders against a commitment
Click Place Order on a confirmed commitment to start an order from it. To start with particular lines, tick them in the grid, then click Place Order in the bar that appears above it. The bar also shows the value of the lines you ticked, and how many have nothing left to buy. Quantities arrive blank, so enter each one before you send the order.
If the vendor already has your PO, your company may also offer Release in SubBase. It makes the lines available for delivery logging without notifying the vendor.
Closing and reopening a commitment
Open a commitment and click Close Commitment when it is fully spent or no longer needed. Existing orders stay linked to it, but it will not be offered for new orders. A closed or cancelled commitment is read-only until you click Reopen Commitment.
How commitments relate to orders and invoices
The order is commitment, then orders, then invoices. You agree the commitment, place orders against it, and invoices arrive against those orders. The totals on the commitment update at each step.
Best practices
Close a commitment rather than cancelling it when the work is done. Existing orders stay linked and you can reopen it later. Cancelling reads as an agreement that was abandoned.
Settle the vendor before you place the first order against a commitment. Once an order is linked, the vendor is fixed and the only way out is a new commitment.
Order in the commitment line's own unit where you can. A line in another unit spends the dollars but leaves the quantity untouched, so Remaining Qty overstates what is left.
Check the Overage columns inside the commitment, not only Total Remaining on the list. Total Remaining stops at 0, so it cannot tell you how far over you are.