Concrete Batch Tracking is where you plan concrete by mix, schedule pours, log what actually arrived, and check the supplier's invoices against it.
Before you start
Concrete Batch Tracking is turned on per company. If Project Management is missing from the top navigation bar, contact us.
By default, Admins, Purchasers and Users can open it, and Admins and Purchasers can create trackers. Your company can change this per role in Company Settings.
Where to find it
Open Project Management in the top navigation bar, then Concrete Batch Tracking. Concrete does not appear in the Commitments list.
What the page shows
The Aggregated budget summary band across the top totals your concrete exposure. It is labelled Counted trackers only. The band includes Budget, Total exposure, Committed cost, Est. $/CY, Forecast $/CY and % Complete.
% Complete is the committed cubic yards as a share of the forecast, with both CY figures beside it. The list has a % Complete column that does the same for each tracker.
With nothing counted yet, the band reads Nothing counted yet. Set a budget on a tracker below and it will total here.
Below the band the list splits under 2 headings, Tracked against a budget and Not counted yet. A tracker joins the total once it has a budget and a projection above $0, from a priced estimate or from pours already logged or scheduled. The headings appear only when there is something in each group.
The status chips and the search box work the same as on the Commitments page: All, Drafted, Confirmed, Partially delivered, Delivered, Closed and Cancelled.
Inside a tracker
A Budget tracking band sits above the tabs. It shows a Concrete card, and a Pump card beside it if your company tracks pumping. Then you get 4 tabs:
Mix List: the mixes on this tracker. By default it shows Estimated CY, Blended Waste %, Blended Waste CY and Total CY, the cost per CY, what is committed, and a forecast for each mix that ends in Cost to Complete, Projected Total and vs Budget.
Pour List: the pours you have scheduled, and the status of each.
Log: what was actually delivered, by pour and mix, with planned and actual costs. Its columns sit under General, Concrete supply and Pump by default. Use Upload Tickets and Review Tickets here to add delivery tickets.
Invoices: the supplier invoices for this tracker's pours. A Next step column says what each one needs: Needs pour assignment, Review variance, Needs approval, Awaiting invoice or Done. Click a card above the table to filter by it.
Log and Invoices appear once the tracker has been saved.
Once the tracker is saved, the header also offers Fee Schedule for the fees and pump rate cards your supplier charges, and Taxes for tax rates. A tax can cover a dated period and be added to new pours in that period automatically.
The Job aggregate bar
A Job aggregate bar along the bottom of the Mix List totals every mix in 3 sections: Estimated (Total CY and Est. Cost), Committed (Committed CY) and Forecast (Cost to Complete and vs Budget). On a narrow window some figures are hidden. Hover over or click a section to open its detail. The Forecast detail adds Committed Cost and Cost to Complete to give the Projected Total, and lists the Largest overruns.
Cost to Complete prices every yard not yet released, scheduled on a pour or not, at the mix's estimated all-in rate (cost per CY plus fees). Releasing a pour moves its cost into Committed without changing the projected total. Yards on a mix with no price are counted apart as unpriced, on the bar's detail and on the Budget tracking cards, so the dollar figures do not include them.
Tracking pumping
An Admin turns this on in Company Settings, under Project Management, Concrete Batch Tracking, General: switch on Track Pumping. Every tracker then gets a Pump card with its own Pump budget. Pump charges never count toward the concrete budget, whether the setting is on or off.
Notes and limits
Each tracker has a primary vendor, and a backup vendor if you want one. The primary vendor is required when you create it.
Your company can rename the Mix List columns, the Log section headings and % Complete, so yours may not match the defaults shown here.
Best practices
Give a tracker a budget as soon as you create it, and price its mixes. Until it has a budget and a projection it sits under Not counted yet and adds nothing to the Aggregated budget summary, so your total exposure reads lower than it is.
Set the backup vendor at the same time as the primary. The primary is required to create the tracker; the backup is not, which is why it gets forgotten.
Watch Forecast $/CY against Est. $/CY as pours are logged. The gap between them is your cost drift on the mix.