Skip to main content

Attach an Order to a Commitment

Already placed the order? Link it, or a quote the vendor answered, to a commitment and choose what happens to lines that are not on it.

Written by Gabby Gutman

Link an order you have already placed, or a quote the vendor has answered, to a commitment. Its lines then count against what you agreed with the vendor.

Before you start

  • Your company must have commitments turned on, and you need permission to edit that type of commitment. If you do not see Attach to Commitment, ask your Admin, or contact us.

  • The order and the commitment must be on the same project. An order can be on only 1 commitment.

  • The order must be at Order Placed, Order Confirmed, Partially Shipped, Shipped, Partially Delivered or Delivered, or be a quote at Quote Provided. These are the default names, and your company may have renamed them.

Steps

  1. Open the order.

  2. Open the more actions menu at the top right and choose Attach to Commitment.

  3. Under Commitment, pick the commitment.

  4. Check the items under Found on the commitment.

  5. For each item under Not on the commitment, choose Draw down, Add or Leave off.

  6. Check the budget line at the bottom. Budget: no change means no new lines.

  7. Click Attach to Commitment.

Attach to Commitment stays disabled until every item under Not on the commitment has a choice.

What happens to each line

  • Found on the commitment: the same material in the same unit is already on the commitment. The item draws down that line, whatever the price. Ordered goes up; the budget does not. If the commitment has 2 or more lines for the material, SubBase picks the one with the same cost code and phase, otherwise the oldest. You can pick a different line beside the item.

  • Draw down: the item draws down a line you pick. If that line is a different material or unit, it counts by dollars only, not quantity.

  • Add: the item becomes a new line on the commitment and raises its budget by the item's cost. Several items of the same material become 1 new line at their quantity-weighted average price. If the commitment is managed by change orders, the increase is recorded as a change order.

  • Leave off: the item stays on the order, marked Not in commitment, and does not count against the commitment.

An item in a different unit from the commitment's line for that material is listed under Not on the commitment.

What happens next

The order is now linked to the commitment, and the commitment's totals update. If you chose Add, a message names the materials added as new lines. The attach is recorded in the commitment's history.

To deal with Not in commitment items later on a material commitment, open the order's more actions menu and choose Add items to commitment, if it is offered.

Undoing an attach

  • There is no button to take an order off a commitment once it is attached.

  • Lines you added stay on the commitment. While the order draws on them, you cannot remove them or lower them below what is ordered. The message starts These lines are already on orders.

  • If you cancel the order, the dialog can offer Cancel and remove lines. It removes the lines the attach added, and their budget, if no other order draws on them. Cancel, keep lines leaves them.

  • Removed lines do not come back on their own. To restore them, add them to the commitment again yourself.

Notes and limits

  • A quote can be attached only once the vendor has answered it.

  • For some companies, Draw down is not offered under Not on the commitment, and budget commitments are not listed. Use Add or Leave off.

Best practices

  • Choose Leave off for a one-off item you do not want in the agreed budget. Add raises the budget, and the new line cannot be removed while the order draws on it.

  • Check the line picked under Found on the commitment when the commitment has the same material on 2 lines with different cost codes. Otherwise the item books to the oldest line.

  • Order in the commitment line's unit. An item in another unit is not found automatically, and if you draw it down it spends dollars but not quantity.

If this doesn't work

Start a chat from the Messenger in the bottom-left of this page, or email [email protected]. Include the order or project number and what you expected to happen.

Related

Did this answer your question?