Reconcile a Concrete Invoice

Check a concrete supplier's invoice against your batch tracker's pours and tickets, fix the tax or accept a variance, and get it ready to approve.

Written by Gabby Gutman

Check a concrete supplier's invoice against the pours and delivery tickets on your batch tracker, settle any differences, and get it ready to approve.

Before you start

  • Your company must have Concrete Batch Tracking turned on. Ask your Admin, or contact us.

  • The invoice must be in SubBase. See Process an Invoice for how invoices arrive.

  • To change a tracker's tax rate or add a fee from the invoice, you need permission to edit concrete trackers, and the invoice must still be editable.

  • Your company decides which roles can accept a variance.

Steps

  1. Open the tracker and go to the Invoices tab.

  2. Click the Needs pour assignment or Review variance card to list what needs you.

  3. Click the invoice number in the list. It opens in the same tab.

  4. Under Pours to reconcile, check the pour. If none is set, choose Select the pour this invoice covers.

  5. Read each row. A row that agrees reads Matched; a row that differs shows the tracker's figure beside the invoice's.

  6. If the tracker is wrong, fix it. On the tax row, use Change rate.

  7. If the invoice is right and differs for a good reason, click Accept variance.

  8. Choose a reason, add a note if you want, and confirm.

  9. Approve the invoice as usual.

What happens next

The invoice header reads Matches the tracker when every row matched by itself, or Variances accepted when every row is settled and at least one needed an accepted variance. Anything still open reads Needs review. On the tracker, the invoice moves to Needs approval, then Done.

If you approve while rows still need review, your company's match setting decides what happens. With a warning you see Lines still need review and can click Approve anyway; that is logged. With a block, an override needs a reason and is recorded with your name and the time.

If the pour has nothing logged and the invoice bills exactly the ordered CY, approving offers Log the ordered CY? and logs those quantities on the Log for you.

What Change rate changes

Change rate replaces the tax on every pour attached to the invoice with the rate you pick. It changes those pours' budgets, and every invoice on those pours is matched again against the new rate. To undo it, use Change rate again and pick the old rate.

Notes and limits

  • The back arrow on the invoice, or your browser's back button, returns you to the Invoices tab with your filters, grouping and scroll position kept.

  • Click a pour chip under Pours to reconcile to open that pour on the tracker's Pour List.

  • Per-truck fees, such as a fuel surcharge per truck, are checked against the trucks on the Log. Each delivery ticket logged is 1 truck, and a load sent back counts as none. A log with no tickets counts 1 truck per 10 CY, rounded up, and so does any typed Actual CY beyond what its tickets cover. Ticket numbers printed on the invoice do not count. The row says whether the tracker's figure is logged or expected, and a difference sends the invoice to review.

  • Invoices from a pump supplier are checked against the pump plan and the pump ticket on the Log. A pump invoice expects no tax.

  • When 2 invoices split one fee, both read as matched once both are in.

  • An invoice that repeats the number of an earlier one is tagged as a possible duplicate. Open it and reject it if it is a copy.

  • A pour reconciled against an invoice cannot be reverted to Pending until you unmatch the invoice lines.

Best practices

  • Fix the tracker when the tracker is wrong, with Change rate or a missing fee. Accept variance settles only that line, so the next invoice on the pour shows the same difference.

  • Set the pour before anything else. An invoice with no pour has nothing to reconcile against, which is why Needs pour assignment comes first.

  • Get the delivery tickets onto the Log before you approve. Per-truck fees are then checked against real trucks rather than an estimate of 1 truck per 10 CY, and with nothing logged, approval stops on No delivery logged.

If this doesn't work

Start a chat from the Messenger in the bottom-left of this page, or email [email protected]. Include the order or project number and what you expected to happen.