The Fee Schedule holds the charges your suppliers bill on a concrete batch tracker: concrete fees, pump rate cards and pump fees. Set it up once per tracker so pours are priced and invoices are checked against it.
Before you start
Your company must have Concrete Batch Tracking turned on. Ask your Admin, or contact us.
You need permission to edit concrete trackers. By default that is the Admin and Purchaser roles.
Save the tracker first. Until then Fee Schedule is greyed out, and hovering it reads Save the commitment first.
Add a concrete fee
Open the tracker and click Fee Schedule in the header.
Click Add Fee.
Enter a Description. Use the name on the supplier's invoice.
Under Fee Type, keep Concrete Fee.
Enter the Rate and pick the Unit Type, such as CY, Truck or Pour.
Tick Auto-apply to new pours if every new pour should carry it.
Click Save & Close, or Save & Add Another.
The fee appears under Concrete Fees.
Add a pump rate card
A rate card is the price list for one pump type. Click Add pump rate, enter the Pump Type (for example 47M), the Hour Rate and the Yardage Rate. Add an Hourly minimum (hrs) if the supplier bills one; hours below it bill the minimum. The card appears under Pump Rate Cards.
On a pour, Add pump puts a pump on site, and you choose it by its pump type. That pump's hours, yardage and card fees are then priced from its rate card.
Add a pump fee
A pump fee, such as a fuel or cleanout charge, is defined once and attached to rate cards.
In Fee Schedule, click Add Fee and choose Pump Fee under Fee Type.
Under Charged, pick how the supplier bills it, such as Per pump hour, Per CY pumped, Flat, once per pump or % of the pump's charges.
Enter the Default rate, or the Default percent for a percent fee.
Under Rate cards, use + Add rate card for each card it applies to, or tick Every rate card.
To charge a different rate on one card, enter it beside that card. Left blank, the card uses the default.
Click Save & Close.
Every pump on a pour that has mixes assigned then gets its own copy of each pump fee on its rate card, priced by SubBase. Pump fees are not offered in the pour's own fee list, so they are never charged twice. Per hour, as invoiced is for hours SubBase does not track, such as drive time: the invoice's hours are taken and only the rate is checked.
Which pours use each fee
A concrete fee with Auto-apply to new pours is added to every new pour on the tracker. Existing pours are not changed. You can still edit or remove it on any pour.
Any other concrete fee is added to a pour by hand, in the pour's fees.
Rate cards and pump fees reach a pour through its pumps. A rate card cannot be auto-applied.
Deleting a fee or rate card
While any pour or mix log uses a fee, a pump fee or a rate card, its Delete button is greyed out. Hover it to see which pours use it, starting In use on pour, and what to do first:
A concrete fee: Remove it from those pours, then delete it.
A pump fee: Take it off its rate cards and save those pours, then delete it.
A rate card: Move those pumps to another rate card, then delete it.
SubBase checks this each time you open Fee Schedule. If the check fails, Delete stays greyed out: close and reopen the Fee Schedule to try again.
Once nothing uses it, Delete asks you to confirm and removes it from the Fee Schedule. No pour carries it by then, so no pour changes. There is no undo; to get it back, add it again.
Notes and limits
A pump fee saved before pump fees were attached to rate cards still works as a fee on the pour as a whole. The Pump Fees table shows it as Added to the pour. To charge it per pump, add it again as a new pump fee.
Your supplier's invoice is checked against these rates. See Reconcile a Concrete Invoice for how differences are shown.
Best practices
Name each fee exactly as the supplier's invoice does. Invoice fee lines match the Fee Schedule by name and rate, so a different name leaves the line unmatched and the invoice needs review.
Set up fees and tick Auto-apply to new pours before you create pours. Auto-apply only reaches new pours, so pours created earlier have to be edited one by one.